North Star Process Plant SMP Installation

Project Overview

Client - Fortescue Metals Group

Location - North Star Magnetite Iron Ore Mine, Pilbara WA

Duration - 8 months

Completion - February 2015

Value - $75M

Personnel on Site - 180

Manhours - 400,000

North Star – Process Plant SMP package consisted of supply, manufacture, installation, construction testing and pre-commissioning of a magnetite processing plant. This was inclusive of crushing, grinding, classification separation right through to production of concentrate and tailings.