Roy Hill Crusher Remediation Project

Project Overview

Client - Tenova TAKRAF

Location - Roy Hill Minesite, Pilbara WA

Duration - 6 months

Completion - July 2016

Value - $3.5M

Personnel on Site - 50

Manhours - 6,520

Centrals were engaged by the vendor of the Crusher Lines in the Roy Hill Mine to perform structural modification to correct and strengthen after critical failures and damage caused during commissioning of the crusher line systems (including feed hopper, apron feeder, primary and secondary sizers, vibrating screens and associated structures). Modifications were required on three separate crusher line systems located with two ROM’s.