Preserving Today. Constructing Tomorrow.

All Enquiries: 1300 796 336

Roy Hill Logistics and Completions Projects

Project Overview

Client - Samsung C&T

Location - Roy Hill Minesite, Pilbara WA

Duration - 28 months

Completion - July 2016

Value - $50M

Personnel on Site - 270

Manhours - 307,652

Centrals was initially engaged by Samsung C&T to provide Logistical and Procurement support for the Completion Works at the Roy Hill Mine Processing Plant. Centrals was subsequently engaged to perform numerous scope for construction and commissioning completion works.

  1. Supply of labour, plant and facilities as requested by Samsung to undertake the materials, logistics, receiving, handling, storage and outgoing of client supplied materials at the Roy Hill Mine Site.
  2. Perform Earthworks Maintenance: Crane Pads for UGL, G&S, Decmil, RCR & EC&M; Road maintenance for all roads on-site and also Marble Bar Road; Building new roads and footpaths; Implementation of TCPs, Upkeep of access road at Sections 9 and 10 in Main Camp
  3. Installation of miscellaneous concrete footings.
  4. Switchroom completion works including AC concrete footings, structural steel, and HVAC installations.
  5. Transformer Compound completion work including supply and install gates/fencing and fire proofing.
  6. Earthworks and installation of concrete foundations for signaling kiosk.
  7. Provide electricians for electrical completions work.
  8. Completion works and punchlisting of Conveyor Systems CVR23 & CVR29, including installation of electrical panels mounts.
  9. Installation of Fire Suppression System to Data Centre Building
  10. Installation and pre-commissioning of mechanical equipment to head end of CVR025.
  11. Installation of water spray bar system to feed hoppers.
  12. Mechanical and electrical works to install the sizer coupler structures at Crusher 1 and 2.
  13. Completion and punchlist works to Crushers 1 and 2.
  14. Geotechnical investigations at COS Tunnel.
  15. Installation of cattle grid at Ginbata Airport.
  16. Concrete remediation patching and grouting to COS Tunnel.

Projects Gallery

« Back to Featured Projects