Roy Hill Crusher Remediation Project
Project Overview
Client - Tenova TAKRAF
Location - Roy Hill Minesite, Pilbara WA
Duration - 6 months
Completion - July 2016
Value - $3.5M
Personnel on Site - 50
Manhours - 6,520
Centrals were engaged by the vendor of the Crusher Lines in the Roy Hill Mine to perform structural modification to correct and strengthen after critical failures and damage caused during commissioning of the crusher line systems (including feed hopper, apron feeder, primary and secondary sizers, vibrating screens and associated structures). Modifications were required on three separate crusher line systems located with two ROM’s.